Indian hydropower provider SJVN said the pumped hydro storage project will be deployed across Darzo Nallah, a tributary of the Tuipui River.
From pv magazine India
SJVN has signed a letter of intent for the construction of a 2.4 GW pumped storage project from the Indian state government of Mizoram. The pumped storage project has been proposed across Darzo Nallah, a tributary of the Tuipui River.
This is SJVN’s first project in the state of Mizoram. It is an on-stream closed-loop type and comprises eight units of 300 MW each.
“The annual energy generation with 95% plant availability shall be 4,993.20 MU. The annual input energy required for pumping water to the upper reservoir has been estimated to be 6,331.66 MU with 95% plant availability,” stated SJVN.
The project is planned to be completed in 72 months. The final agreement between SJVN and the government of Mizoram shuould be signed within three months.
“}]]